Before demolition: decisions
Pick your fixtures first. Toilet, basin, vanity, tapware, shower head, bath. Every one of them has a set out: where the pipes need to come out of the wall or floor. The plumber cannot rough in without knowing what is going where. Changing a vanity after rough in means moving pipes in a finished wall. Decide early and have the spec sheets on site.
Step 1: strip out
Old fixtures come out and the plumber caps the water and drain points so the room is safe to work in. This is also when we find the surprises: old galvanised pipe, a rotten floor under the shower, a drain with no fall. Budget for a little of this on any bathroom over 25 years old.
Step 2: rough in
With the walls open, we run new hot and cold water lines, position the drain points for the shower, basin, bath and toilet, and set the in wall mixer bodies and cistern frames if you are using them. Everything is pressure tested. Then the room is handed to the builder for sheeting and screeding. Read our guide on the rough in checklist for a full list of what is set at this stage.
Planning a bathroom? Call 0428 411 487 before the layout is final.
Step 3: waterproofing and tiling
Not us, but the sequence matters. The waterproofer needs the drain points and the floor waste in their final position. The tiler needs the mixer bodies and spouts at the right depth for the tile and glue thickness. We coordinate with both so the finished wall lines up with the fittings.
Step 4: fit off
After tiling, we come back and fit the visible parts: taps, spouts, shower rail, basin and mixer, toilet pan and cistern, bath waste. Everything is connected, tested and sealed. The room goes live.
Compliance
A bathroom renovation that moves or adds fixtures is notifiable work in Queensland. We lodge the paperwork and you receive the Form 4. Keep it. Read our guide on Form 4s.
Common mistakes
Ordering a wall hung toilet without checking the wall can take the frame. Choosing a freestanding bath without planning where the floor waste and the tap go. Moving the toilet further than the drain fall allows. Read our guide on moving a toilet or shower for what affects the cost.
Timeline
Plumbing takes a day or two at rough in and a day at fit off. The gaps between are the builder, waterproofer and tiler. A typical bathroom runs three to five weeks from strip out to finished.
Allied Plumbing handles bathroom renovation plumbing across the Sunshine Coast and Noosa. QBCC Licence 15589829. MPAQ member. 15 years in the trade. Call 0428 411 487 or get in touch online.